Kamarajar Port gets Rs 4,288 crore Second Container Terminal Approval: 2 million TEU capacity to be added near Chennai

5 hours ago 2

Cabinet Approves Rs 4,288 Crore Second Container Terminal at Kamarajar Port Under PPP Mode

The Cabinet Committee on Economic Affairs, chaired by Prime Minister Narendra Modi, has approved the development of a Second Container Terminal at Kamarajar Port Limited (KPL), near Chennai, on a Design, Build, Finance, Operate and Transfer (DBFOT) basis under the Public Private Partnership mode. The estimated cost is Rs 4,288.26 crore including GST, and the terminal will add 2.0 million TEUs of annual capacity.

The terminal will be 900 metres long with a berth width of 30 metres and a design draft of 18 metres. It will be built in two phases: Phase I with 1.1 million TEUs and Phase II with 0.9 million TEUs. It is designed to handle large mainline container vessels of up to 24,346 TEUs and 400 metres in length, which would strengthen KPL's links with international shipping routes.

The PPP component costs Rs 4,288.26 crore, of which Rs 2,429.32 crore is for Phase I and Rs 1,858.94 crore for Phase II. The selected concessionaire will arrange the investment and recover it through user charges under the Concession Agreement and the applicable tariff framework. Separately, KPL will bear an estimated Rs 450 crore for dredging. The government says there will be no financial implication for the Government of India for the PPP component.

The concessionaire will be chosen through a transparent, open global bidding process.

The concession period is 40 years, including a 48-month construction period. Phase I is to be completed within 24 months of the Date of Award of Concession, with commercial operations starting in the 25th month. Phase II will be built between the 25th and 48th months, with full operations beginning in the 49th month. Environmental and other clearances are to be obtained in a time-bound manner before the bid due date.

KPL handled 49.08 million tonnes of cargo and 1,008 vessels in FY 2025-26, including more than 7 lakh TEUs of containers. Its existing container terminal has an installed capacity of 0.8 million TEUs and handled about 0.7 million, a utilisation of roughly 88 per cent, which leaves little room for growth.

Container traffic in India has grown at a compound annual rate of about 7 per cent over five years, while KPL's has grown about 9.9 per cent. The feasibility study projects continued growth in the south-eastern region. The terminal is meant to serve export-import cargo from the Chennai-Ennore industrial region and the wider southern hinterland, including automobiles and components, engineering goods, electronics, chemicals and other manufactured products.

The government expects the additional capacity to give Tamil Nadu's industrial clusters and adjoining states another gateway. The 18-metre draft and ability to take large ships are expected to enable direct calls by mainline vessels and reduce dependence on foreign deep-water hub ports and the feeder costs that come with them. The project is also expected to improve logistics efficiency, support manufacturing and trade, and raise the port's revenue.

It is projected to generate employment for about 750 people directly and indirectly during construction and about 800 during operations. The government says it supports Atmanirbhar Bharat by augmenting domestic port capacity for industries and original equipment manufacturers in Tamil Nadu, Karnataka, Andhra Pradesh, Telangana and neighbouring areas, and that it aligns with Maritime India Vision 2030 and Maritime Amrit Kaal Vision 2047.

Formerly Ennore Port Limited, Kamarajar is one of India's 12 major ports and is wholly owned by Chennai Port Authority under the Ministry of Ports, Shipping and Waterways. It handles coal, petroleum, oil and lubricants, LNG, LPG, containers, automobiles and general cargo. In FY 2025-26 it recorded revenue of about Rs 1,280 crore and a profit before tax of Rs 924 crore, with cargo growing at a compound annual rate of 13.64 per cent over five years.

The next steps are the bidding process and the award of the concession. The pace of clearances and dredging will decide whether the 24-month target for Phase I is met. The figures for capacity, cost and jobs are official projections, and actual outcomes will depend on execution and on how container demand grows.