Rushikonda project substantially altered hill’s natural topography, Central expert panel tells Andhra HC

43 minutes ago 1
A view of the structures built on Rushikonda hill in Visakhapatnam during the YSRCP government’s term. A Central expert committee has told the Andhra Pradesh High Court that the project substantially altered the hill’s natural topography.

A view of the structures built on Rushikonda hill in Visakhapatnam during the YSRCP government’s term. A Central expert committee has told the Andhra Pradesh High Court that the project substantially altered the hill’s natural topography. | Photo Credit: K.R. Deepak

An expert committee constituted by the Ministry of Environment, Forest and Climate Change (MoEF&CC) to assess the impact of violations in the construction of the luxurious tourist resort on the eco-sensitive Rushikonda hill in Visakhapatnam has concluded that the execution of the project resulted in substantial alteration of the natural hill topography. The committee submitted its report to the High Court of Andhra Pradesh on November 25, 2026.

The palatial structures built during the YSR Congress Party (YSRCP) government’s term were widely said to be meant as the camp office of former Chief Minister Y.S. Jagan Mohan Reddy. They came up after the Andhra Pradesh Tourism Development Corporation (APTDC) Haritha resort on the hill was demolished in 2021. The project ran into controversy, with environmentalists and political activists objecting to the construction and approaching the court.

The committee recommended that restoration measures be carried out under the supervision of the competent regulatory authorities and monitored periodically through a multidisciplinary mechanism comprising representatives of relevant scientific and regulatory organisations.

The hill’s topography was altered through extensive excavation, hill cutting and levelling, and the generation of large quantities of excavated soil, muck and construction and demolition waste, a significant quantity of which was dumped at several locations, including areas in the Coastal Regulation Zone, the committee found. This affected the coastal landscape and the ecological characteristics of the area, it said.

The committee stated that these activities caused degradation of land resources, alteration of the natural terrain, loss of ecological functions, impairment of the aesthetic and recreational value of the coastal landscape, and loss of potential land-use opportunities.

These impacts extended beyond the immediate project area, requiring systematic ecological restoration based on scientific principles, the committee said.

The panel said restoration should be undertaken through a scientifically prepared Environmental Restoration Plan formulated by institutions with expertise in coastal ecology, geomorphology, geotechnical engineering, biodiversity and environmental conservation.

The committee advised that long-term monitoring of slope stability, coastal geomorphology, shoreline changes, biodiversity, vegetation recovery, and other environmental parameters be taken up to evaluate the effectiveness of the restoration measures and facilitate adaptive management wherever necessary.

The MoEF&CC committee took into consideration the findings of a panel nominated by the High Court following a writ petition filed by former corporator P.V.L.N. Murthy, who alleged flagrant violation of norms by the APTDC in the massive construction activity.

Costs and future use

The Comptroller and Auditor General (CAG) found in April that the project’s cost had risen from ₹164 crore to ₹350.16 crore after it was restructured into three phases and that it had been approved without a Detailed Project Report or the judicial preview required for works costing over ₹100 crore. As of February 2024, ₹306.93 crore had been spent.

In June, a Group of Ministers constituted by the State government recommended that the buildings be run as a hospitality project under a public-private partnership, with some blocks set aside for public use. The government was spending about ₹25 lakh a month on their upkeep, Finance Minister Payyavula Keshav said at the time.

Published - November 26, 2026 07:19 pm IST

Read Entire Article